Refinishing the EIFS canopy at Casey Stadium's South Gate, Albany
The canopy over the South Gate of the University at Albany's Casey Stadium has an EIFS soffit, and its purple finish had gone dull and chalky. In summer 2026 we cleaned it, repaired it and refinished it as part of our painting contract for the stadium.

At a glance
- Client
- University at Albany (Public works)
- Location
- Albany
- Completed
- August 2026
- Our role
- Prime contractor on a competitively bid, bonded, prevailing-wage painting contract
- Scope
- Cleaned, repaired and refinished the faded EIFS canopy soffit at the South Gate.
- Access
- Scaffold
- Status
- Complete
- The Dom Construction Group LLC
Before and after
Before · April 2026
Before: chalked, faded canopy underside at the site walk · Casey Stadium, Albany · April 2026 Before · July 2026
Before: the faded South Gate soffit · Casey Stadium, Albany · July 2026 After · August 2026
After: the refinished South Gate canopy · Casey Stadium, Albany · August 2026
The problem at Casey Stadium
A gate canopy is a large, flat underside right over the entrance, so every patch of fading shows. At Casey Stadium that underside is EIFS, finished in purple. By 2026 the finish had faded and chalked, and it looked patchy next to the stadium steel, which was about to get fresh paint under the same contract.
What we found at Casey Stadium
At the site walk in April 2026 the chalking ran across the whole face of the soffit, not in a few spots. By July, with the job under way, the fade was still uneven from panel to panel. Chalk is the top of a coating breaking down into powder. A new coat laid over it has nothing solid to hold on to, so the order of work matters more than the paint.
The job had two other limits:
- A state contract. The Office of the State Comptroller had to approve the contract before any material could be ordered, and product data and safety data sheets were submitted and approved before work started.
- A working facility. Parts of the stadium job ran as evening shifts under the stadium lights to hold the schedule.
What we did at Casey Stadium
- Cleaned the soffit so the new finish would bond to sound material, not to chalk.
- Repaired the EIFS surface where it needed it, before any coating went on.
- Refinished the canopy in a color matched to the stadium's color scheme, working from scaffold.
We were the prime contractor on a competitively bid, bonded, prevailing-wage painting contract. The EIFS canopy was one part of it; the rest of the contract repainted the stadium's structural steel, and that side of the job is written up on The Dom Construction Group's site.
The result at Casey Stadium
The South Gate canopy has one even color again, and it sits right with the repainted steel around it. The work was finished in August 2026, and the punch list was completed with the university's project representative.
If your building has a faded or chalky EIFS wall, it may need the same treatment rather than replacement: see EIFS recoating. Owners and facility managers can read how we handle campuses and other occupied buildings on our commercial EIFS and stucco page.
More on recoating and public work
- EIFS and stucco recoating
When a faded wall needs a new finish rather than a rebuild.
- Commercial and public work
Campuses, storefronts, apartment buildings and GC packages.
- All projects
More EIFS and stucco jobs, by town and month.
- More on this job at The Dom Construction Group
The steel repaint and the rest of the stadium contract.
Same problem? Text a photo.
A faded or chalky EIFS wall can often be cleaned, repaired and refinished. One close-up and one wide shot is enough for a first look.